Question

The axis of a gravity dam is the ______________________

a.

line of the crown of the dam on the downstream side

b.

line of the crown of the dam on the upstream side

c.

centre-line of the top width of the dam

d.

line joining mid-points of the base

Answer: (b).line of the crown of the dam on the upstream side

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. The axis of a gravity dam is the ______________________

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. Presence of tail-water in a gravity dam ____________________

Q. The provision of drainage gallery in a gravity dam helps in reducing ____________________

Q. Which of the following attempts are made to reduce the uplift in order to economize on the provided section of a concrete gravity dam?

i. Providing drainage gallery to collect seepage water
ii. Constructing cut-off under upstream face
iii. Pressure grouting in dam foundation
iv. Provision of shear keys or keyways

Q. Transverse joints in concrete gravity dams are the ___________________________

Q. Leakage through the transverse joints in a gravity dam is prevented by ____________

Q. In order to reduce uplift on a gravity dam, the type of grouting done is ____________________

Q. The general value of lift for concrete is taken as __________________

Q. The horizontal joints that extends through the entire width of the dam section and are developed at each lift height is called as ___________________

Q. Which of the following joints justifies the two-dimensional analysis of gravity dams?

Q. The foundation pressure used in the pressure grouting is equal to _________________

Q. Which of the following earth dam is suitable only on impervious foundation?

Q. Which of the following zone in Zoned type embankment prevents piping through cracks?

Q. Which of the following soil material is most preferred for the central core material of zoned embankment type dam?

Q. Which embankment has the thickness of the diaphragm at an elevation less than 10 meters or the height of the embankment above the corresponding elevation?

Q. The blanket in earth dam is provided ___________________

Q. Which of the following statement is correct with reference to earthen dams?

Q. During the construction of an earthen dam by hydraulic fill method, development of pore pressure becomes important in the __________________

Q. The process of laying and compacting earth in layers by power rollers under OMC for construction of earthen dams is known as ______________________

Q. The central core of the zoned embankment type earth dam ________________________

Q. Which type of dam is suitable on shallow pervious foundations?

Recommended Subjects