Question

Which of the following attempts are made to reduce the uplift in order to economize on the provided section of a concrete gravity dam?

i. Providing drainage gallery to collect seepage water
ii. Constructing cut-off under upstream face
iii. Pressure grouting in dam foundation
iv. Provision of shear keys or keyways

a.

i and ii

b.

i, ii and iii

c.

i, ii and iv

d.

i, ii, iii and iv

Answer: (b).i, ii and iii

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Which of the following attempts are made to reduce the uplift in order to economize on the provided section of a concrete gravity dam? i. Providing drainage gallery to collect...

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. Transverse joints in concrete gravity dams are the ___________________________

Q. Leakage through the transverse joints in a gravity dam is prevented by ____________

Q. In order to reduce uplift on a gravity dam, the type of grouting done is ____________________

Q. The general value of lift for concrete is taken as __________________

Q. The horizontal joints that extends through the entire width of the dam section and are developed at each lift height is called as ___________________

Q. Which of the following joints justifies the two-dimensional analysis of gravity dams?

Q. The foundation pressure used in the pressure grouting is equal to _________________

Q. Which of the following earth dam is suitable only on impervious foundation?

Q. Which of the following zone in Zoned type embankment prevents piping through cracks?

Q. Which of the following soil material is most preferred for the central core material of zoned embankment type dam?

Q. Which embankment has the thickness of the diaphragm at an elevation less than 10 meters or the height of the embankment above the corresponding elevation?

Q. The blanket in earth dam is provided ___________________

Q. Which of the following statement is correct with reference to earthen dams?

Q. During the construction of an earthen dam by hydraulic fill method, development of pore pressure becomes important in the __________________

Q. The process of laying and compacting earth in layers by power rollers under OMC for construction of earthen dams is known as ______________________

Q. The central core of the zoned embankment type earth dam ________________________

Q. Which type of dam is suitable on shallow pervious foundations?

Q. What is the U.S.B.R recommended value for freeboard when the height of the dam is more than 60 m?

Q. What is the recommended formula for top width of a very low dam?

Q. What is the Terzaghi’s recommended value of U/s side slope for earth dam of height less than 15m of homogenous silty clay?

Recommended Subjects

Are you eager to expand your knowledge beyond Irrigation Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!