Balanced Scorecard MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Balanced Scorecard, a fundamental topic in the field of Cost Accounting. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Balanced Scorecard MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Balanced Scorecard mcq questions that explore various aspects of Balanced Scorecard problems. Each MCQ is crafted to challenge your understanding of Balanced Scorecard principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Cost Accounting tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Balanced Scorecard MCQs are your pathway to success in mastering this essential Cost Accounting topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Balanced Scorecard. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Balanced Scorecard knowledge to the test? Let's get started with our carefully curated MCQs!

Balanced Scorecard MCQs | Page 7 of 7

Discover more Topics under Cost Accounting

Q61.
The on-time performance and customer-response time are the examples of
Discuss
Answer: (a).customer measures
Discuss
Answer: (d).all of above
Q63.
If the cost of direct materials use in the goods sold is $5000 and the total revenues are $9000 then the throughput contribution would be
Discuss
Answer: (c).$4,000
Q64.
The time a company takes until a good is produced after order placement is known as
Discuss
Answer: (a).manufacturing lead time
Q65.
The factors identified by cause and effect diagrams include
Discuss
Answer: (d).all of above
Q66.
The delivery of goods by the time it is contracted to be delivered is known as
Discuss
Answer: (d).on-time performance
Q67.
The value added manufacturing time is divided by total manufacturing, is to calculate
Discuss
Answer: (d).manufacturing cycle efficiency
Q68.
The chart which represents how regularly the defect occurs in production process is classified as
Discuss
Answer: (d).Pareto chart
Q69.
If the manufacturing cycle efficiency is 0.725 and the total manufacturing time is 45 minute, then the value added manufacturing time will be
Discuss
Answer: (c).32.625