Dam Design and Construction MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Dam Design and Construction, a fundamental topic in the field of Irrigation Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Dam Design and Construction MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Dam Design and Construction mcq questions that explore various aspects of Dam Design and Construction problems. Each MCQ is crafted to challenge your understanding of Dam Design and Construction principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Irrigation Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Dam Design and Construction MCQs are your pathway to success in mastering this essential Irrigation Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Dam Design and Construction. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Dam Design and Construction knowledge to the test? Let's get started with our carefully curated MCQs!

Dam Design and Construction MCQs | Page 8 of 16

Discover more Topics under Irrigation Engineering

Q71.
Which of the following component of a buttress dam is also called counterfort?
Discuss
Answer: (b).Buttress
Q72.
Which of the following type of dam requires very strong and stable foundations and is not in use as much as the other types?
Discuss
Answer: (c).Columnar buttress type dam
Q73.
Which of the following is the earliest recorded multiple arch buttress dam?
Discuss
Answer: (a).Meer Alam dam in India
Q74.
In a simple deck slab buttress dam of a given height, the buttress spacing can be increased by increasing the upstream slope.
Discuss
Answer: (a).True
Q75.
When the reservoir is empty, the maximum vertical stress equal to ________________
Discuss
Answer: (a).At heel = 2W/B and at toe = 0
Q76.
The two-dimensional stability analysis of gravity dams proves better for U-shaped valleys than for V-shaped valleys.
Discuss
Answer: (a).True
Q77.
Calculate the value of minimum base width for an elementary triangular concrete gravity dam supporting 72 m height of reservoir water and full uplift? (Take specific gravity of concrete as 2.4 and coefficient of friction as 0.7)
Discuss
Answer: (d).73.5 m
Q78.
For usual values of permissible compressive stress and specific gravity of concrete, a high concrete gravity is the one whose height exceeds ______________
Discuss
Answer: (c).88 m
Q79.
For triangular dam section of height H for just no tension under the action of water pressure, self-weight and uplift pressure, the minimum base width required is _____________
Discuss
Answer: (d).H / (S-1)^1/2
Q80.
If the eccentricity of the resultant falls outside the middle third, the ultimate failure of the dam occurs by ______________
Discuss
Answer: (a).tension