Dam Design and Construction MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Dam Design and Construction, a fundamental topic in the field of Irrigation Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Dam Design and Construction MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Dam Design and Construction mcq questions that explore various aspects of Dam Design and Construction problems. Each MCQ is crafted to challenge your understanding of Dam Design and Construction principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Irrigation Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Dam Design and Construction MCQs are your pathway to success in mastering this essential Irrigation Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Dam Design and Construction. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Dam Design and Construction knowledge to the test? Let's get started with our carefully curated MCQs!

Dam Design and Construction MCQs | Page 5 of 16

Discover more Topics under Irrigation Engineering

Q41.
Calculate the value of free-board that should be provided for a reservoir having a wind velocity of 92 km/h and it extends up to 18 km upstream.
Discuss
Answer: (c).2.25 m
Q42.
The type of arch dam which generally requires overhangs at abutments is of ________________________
Discuss
Answer: (c).constant angle type
Q43.
Which of the following forces is the least important in the design of arch dams?
Discuss
Answer: (b).Uplift pressure
Q44.
Which of the following theory is the most accurate method to design arch?
Discuss
Answer: (c).The trial load method
Discuss
Answer: (b).Any horizontal arch ring is independent of the arch rings below and above
Q46.
The upward acceleration of dam due to seismic activity will ________________________
Discuss
Answer: (a).increase the base pressure
Q47.
What is the average value of acceleration that is sufficient for high dams in seismic zones?
Discuss
Answer: (a).0.1g to 0.15g
Q48.
What is Von Karman’s formula for hydrodynamic force (Pβ‚‘)?
Discuss
Answer: (d).Pβ‚‘ = 0.555.Kβ‚•. Yw H²
Q49.
The factor of safety against overturning generally varies between ___________
Discuss
Answer: (a).2 to 3
Q50.
What is the maximum permissible tensile stress for high concrete gravity dam under worst conditions?
Discuss
Answer: (a).500 KN/m²