Dam Design and Construction MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Dam Design and Construction, a fundamental topic in the field of Irrigation Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Dam Design and Construction MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Dam Design and Construction mcq questions that explore various aspects of Dam Design and Construction problems. Each MCQ is crafted to challenge your understanding of Dam Design and Construction principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Irrigation Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Dam Design and Construction MCQs are your pathway to success in mastering this essential Irrigation Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Dam Design and Construction. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Dam Design and Construction knowledge to the test? Let's get started with our carefully curated MCQs!

Dam Design and Construction MCQs | Page 5 of 16

Discover more Topics under Irrigation Engineering

Discuss
Answer: (b).The resultant force for all conditions of loading must pass through the middle third of the base
Q42.
An arch dam looks like a single arch in _________________
Discuss
Answer: (a).plan
Q43.
A non-vertical arch dam is known as a _______________
Discuss
Answer: (d).both double curvature and shell arch dams
Q44.
Greater is the wall curvature in an arch dam, greater will be the economy in the dam thickness.
Discuss
Answer: (a).True
Q45.
Which of the following is the most economical type of arch dam?
Discuss
Answer: (c).Constant angle type
Q46.
A constant angle arch dam when compared to constant radius arch dam utilizes concrete quality of about ______________
Discuss
Answer: (a).43%
Q47.
Which among the following type of dam section is expected to be the thinnest and the most economical?
Discuss
Answer: (b).Shell-arch dam
Q48.
The bottom portion of a concrete or a masonry gravity dam is usually stepped in order to _______
Discuss
Answer: (b).increase the shear strength
Q49.
The governing compressive stress in a concrete gravity dam which should not be allowed to exceed the permissible value of about 3000 KN/m² while analyzing full reservoir case is ____________________
Discuss
Answer: (b).the major principal stress at toe
Q50.
If the uplift increases and the net effective downward force reduces, the resultant will shift towards the toe.
Discuss
Answer: (a).True