Continuous Process Improvement MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Continuous Process Improvement, a fundamental topic in the field of Total Quality Management. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Continuous Process Improvement MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Continuous Process Improvement mcq questions that explore various aspects of Continuous Process Improvement problems. Each MCQ is crafted to challenge your understanding of Continuous Process Improvement principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Total Quality Management tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Continuous Process Improvement MCQs are your pathway to success in mastering this essential Total Quality Management topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Continuous Process Improvement. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Continuous Process Improvement knowledge to the test? Let's get started with our carefully curated MCQs!

Continuous Process Improvement MCQs | Page 5 of 9

Q41.
‘To define the problem’ is a part of which phase of PDCA cycle?
Discuss
Answer: (a).Plan
Q42.
‘To determine the quality objectives and the critical factors’ is a part of which phase of PDCA cycle?
Discuss
Answer: (a).Plan
Q43.
‘To generate possible solutions’ and ‘To select the most feasible solution’ is a part of which phase of PDCA cycle?
Discuss
Answer: (a).Plan
Q44.
It is recommended to try the plan made in the planning phase on a limited scale or conduct and experiment to test the proposed improvement.
Discuss
Answer: (a).True
Q45.
‘To train all employees in quality improvement methods and techniques’ is a part of which phase of PDCA cycle?
Discuss
Answer: (b).Do
Q46.
‘To form project team that will focus on quality improvement processes’ is a part of which phase of PDCA cycle?
Discuss
Answer: (b).Do
Q47.
‘To evaluate the trial project with the already decided performance indicators’ is a part of which phase of PDCA cycle?
Discuss
Answer: (c).Check
Q48.
Which of the following decision is not part of the ‘Action’ phase?
Discuss
Answer: (d).Defining the problem
Q49.
‘To document the standard procedures regarding improvement’ is a part of which phase of the PDCA cycle?
Discuss
Answer: (d).Act
Q50.
5S is defined as a housekeeping technique used to establish and maintain a productive and quality environment in an organization.
Discuss
Answer: (a).True