Total Productive Maintenance MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Total Productive Maintenance, a fundamental topic in the field of Total Quality Management. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Total Productive Maintenance MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Total Productive Maintenance mcq questions that explore various aspects of Total Productive Maintenance problems. Each MCQ is crafted to challenge your understanding of Total Productive Maintenance principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Total Quality Management tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Total Productive Maintenance MCQs are your pathway to success in mastering this essential Total Quality Management topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Total Productive Maintenance. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Total Productive Maintenance knowledge to the test? Let's get started with our carefully curated MCQs!

Total Productive Maintenance MCQs | Page 5 of 6

Q41.
In which stage of TPM development is the development of the early equipment management program carried out?
Discuss
Answer: (a).TPM implementation stage
Q42.
Training conducted to improve the operation and maintenance skills are carried out in the TPM implementation stage of TPM development?
Discuss
Answer: (a).True
Q43.
In which stage of TPM development a scheduled maintenance program for the maintenance department developed?
Discuss
Answer: (d).TPM implementation stage
Q44.
If availability is 85%, performance efficiency is 50%, and the rate of quality products is 98%, then find out the overall equipment effectiveness?
Discuss
Answer: (a).42%
Q45.
What is the quality score if an asset produces 15000 units out of which 500 are defective?
Discuss
Answer: (c).96.67%
Q46.
A machine that was supposed to run for 10 hours suffers a breakdown and runs only for 9 hours. Calculate availability.
Discuss
Answer: (b).90%
Q47.
If the loading time is 400 minutes and downtime is 60 minutes, calculate availability.
Discuss
Answer: (c).85%
Q48.
If the theoretical cycle time per unit is 0.5 minutes/unit, the number of units is 400, and the operating time is 400 minutes, calculate performance efficiency.
Discuss
Answer: (d).50%
Q49.
If the overall equipment effectiveness is 40%, availability 82%, quality score 96%, calculate the performance efficiency?
Discuss
Answer: (a).50.8%
Q50.
Improved safety is one of the benefits of implementing TPM.
Discuss
Answer: (a).True
Page 5 of 6