Sewage Disposal and Construction of Sewers MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Sewage Disposal and Construction of Sewers, a fundamental topic in the field of Waste Water Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Sewage Disposal and Construction of Sewers MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Sewage Disposal and Construction of Sewers mcq questions that explore various aspects of Sewage Disposal and Construction of Sewers problems. Each MCQ is crafted to challenge your understanding of Sewage Disposal and Construction of Sewers principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Waste Water Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Sewage Disposal and Construction of Sewers MCQs are your pathway to success in mastering this essential Waste Water Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Sewage Disposal and Construction of Sewers. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Sewage Disposal and Construction of Sewers knowledge to the test? Let's get started with our carefully curated MCQs!

Sewage Disposal and Construction of Sewers MCQs | Page 6 of 12

Discover more Topics under Waste Water Engineering

Q51.
If sizes of the sewers are __________ choking problems are less.
Discuss
Answer: (a).Large
Q52.
Which of the following is a disadvantage with respect to the size of the sewers?
Discuss
Answer: (c).Handling and transportation
Q53.
In which kind of cities are combined systems used?
Discuss
Answer: (a).Less population
Q54.
In partial systems, there is no over load on the treatment plants.
Discuss
Answer: (b).False
Q55.
The treatment is costly in which of the following systems?
Discuss
Answer: (a).Combined
Q56.
The process that involves connecting pipelines and sewer appurtenances to transport waste to sewage treatment centres is called?
Discuss
Answer: (c).Sewer construction
Q57.
Pipeline networks are designed by engineers and installed by sewer contractors in accordance with federal and state regulations.
Discuss
Answer: (a).True
Q58.
Sewer systems can also be referred as _________
Discuss
Answer: (b).Sewerage
Q59.
On which of the factors mentioned below, the type of the sewer installed does not depend on?
Discuss
Answer: (d).storm water
Q60.
__________ is required to transport storm water runoff from roofs, parking lots, streets, and highways to a point of discharge.
Discuss
Answer: (b).Storm sewers