Question

In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

a.

whose output exceeds 67% efficiency

b.

on the percentage of time saved

c.

on the percentage of time worked

d.

on the percentage of standard time

Posted under Mechanical Engineering

Answer: (a).whose output exceeds 67% efficiency

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. M.T.M. is used to

Q. A dummy activity in a net work diagram

Q. When slack of an activity is positive

Q. For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be

Q. Follow-up prescribes the sequence of operations to be followed.

Q. Dummy activities are used to

Q. Which of the following statement is wrong?

Q. The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of

Q. Standard time is equal to

Q. In inventory control, the economic ordering quantity is obtained by the quantity whose procurement cost is equal to inventory carrying cost.

Q. The essential condition for the decompression of an activity is that

Q. Time study is carried out

Q. Two alternatives can produce a product. First has a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is

Q. Which of the following are the principles of material handling?

Q. The product layout

Q. An event is a function of two or more activities.

Q. The mathematical technique for finding the best use of limited resources of a company in the maximum manner is known as

Q. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

Q. Scheduling

Q. F. W. Taylor introduced a system of organisation known as

Recommended Subjects

Are you eager to expand your knowledge beyond Mechanical Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!