Question

While preparing a detailed estimate

a.

Dimension should be measured correct to 0.01 m

b.

Area should be measured correct to 0.01 sqm

c.

Volume should be measured correct to O.Olcum

d.

All the above.

Posted under Civil Engineering

Answer: (d).All the above.

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. While preparing a detailed estimate

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. The plinth area of a building not includes

Q. For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is

Q. The minimum width of a septic tank is taken

Q. The item of the brick structure measured in sq.m, is

Q. The inspection pit or chamber is a manhole provided in a base drainage system

Q. Pick up the excavation where measurements are made in square metres for payment.

Q. The expected out turn of 2.5 cm cement concrete floor per manson per day

Q. A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.

Q. The order of booking dimensions is

Q. As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken

Q. Pick up the item of work not included in the plinth area estimate

Q. Pick up the correct statement from the following:

Q. The brick work is measured in sq metre, in case of

Q. Brick walls are measured in sq. m if the thickness of the wall is

Q. The most reliable estiamte is

Q. The expected out turn of 12 mm plastering with cement mortar is

Q. The main factor to be considered while preparing a detailed estimate, is

Q. The damp proof course (D.P.C.) is measured in

Q. Pick up the incorrect statement regarding a master trap from the following :

Q. The concrete work for the following part of the building of specified thickness is measured in square metres

Recommended Subjects

Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!