Question

Pick up the correct statement from the following:

a.

In order to check up the average depth of excavation, 'Dead mans' are left at the mid-widths of borrow pits

b.

The earthwork calculation in excavation is made from the difference in levels obtained with a level

c.

The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers

d.

All the above.

Posted under Civil Engineering

Answer: (d).All the above.

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Pick up the correct statement from the following:

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by prismoidal formula, is

Q. The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended

Q. Pick up the correct statement from the following:

Q. The weight of an item is measured correct to nearest

Q. Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds

Q. Pick up the correct statement from the following:

Q. The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is

Q. Pick up the correct statement from the following:

Q. The following item of earth work is not measured separately.

Q. The rate of payment is made for 100 cu m (per % cu m) in case of

Q. Pick up the incorrect statement from the following:

Q. The measurement is made in square metre in case of

Q. Berms are provided in canals if these are

Q. Pick up the incorrect statement from the following:

Q. Carpet area does not include the area of

Q. The trap which is provided to disconnect the house drain from the street sewer is called

Q. Pick up the incorrect statement from the following:

Q. Pick up the correct statement regarding the centre line method of estimating a building

Q. The brick work is not measured in cu m in case of

Q. The rate of an item of work depends on

Recommended Subjects

Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!