Question

Pick up the correct statement from the following:

a.

The incidental expenses of a miscellaneous character which could not be predicted during preparation of the estimate, is called contingencies

b.

Additional supervising staff engaged at work site, is called work charged establishment

c.

Detailed specifications specify qualities, quantities and the proportions of materials to be used for a particular item

d.

All the above.

Answer: (d).All the above.

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Pick up the correct statement from the following:

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is

Q. Pick up the correct statement from the following:

Q. The following item of earth work is not measured separately.

Q. The rate of payment is made for 100 cu m (per % cu m) in case of

Q. Pick up the incorrect statement from the following:

Q. The measurement is made in square metre in case of

Q. Berms are provided in canals if these are

Q. Pick up the incorrect statement from the following:

Q. Carpet area does not include the area of

Q. The trap which is provided to disconnect the house drain from the street sewer is called

Q. Pick up the incorrect statement from the following:

Q. Pick up the correct statement regarding the centre line method of estimating a building

Q. The brick work is not measured in cu m in case of

Q. The rate of an item of work depends on

Q. Pick up the correct statement from the following:

Q. Pick up the correct statement from the following:

Q. The expected out turn of half brick partition wall per mason per day is

Q. If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is

Q. The floor area includes the area of the balcony up to

Q. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

Recommended Subjects

Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!