Question
a.
The arrangement is generally constructed when the drain is very big as compared to the section of the canal
b.
The damage caused by floods is not rare
c.
The CD works are more liable to damage than the earthwork of the canal
d.
The perennial canal is not open to inspection or maintenance
Posted under Irrigation Engineering
Interact with the Community - Share Your Thoughts
Uncertain About the Answer? Seek Clarification Here.
Understand the Explanation? Include it Here.
Q. Which of the following is a disadvantage of CD works carrying drainage over the canal?
Similar Questions
Explore Relevant Multiple Choice Questions (MCQs)
Q. The canal alignment is finalized only after finalizing the CD works.
View solution
Q. The relative bed levels of the canal and the drainage may be changed and manipulated by _________________
View solution
Q. The selection of the CD works depends on?
i. Selecting canal alignment
ii. Position of water-table and availability of dewatering equipment
iii. Suitability of soil for embankment
iv. Availability of funds
View solution
Q. Inlets and Outlets are inferior to aqueduct or super-passage type of work.
View solution
Q. In order to reduce the CD works, the artificial canals are generally aligned along the ridgeline.
View solution
Q. The type of canal alignment which involves maximum CD works is a ______________
View solution
Q. What is Lacey’s equation for fixing the approximate value of the required waterway for the drain?
View solution
Q. The maximum permissible reduction in the waterway from Lacey’s perimeter is _______
View solution
Q. The permissible velocity through the barrels is generally limited to _____________
View solution
Q. Which of the following method is applicable for the design of channel transition when the water depths of the flumed and unflumed section are the same or maybe different?
View solution
Q. In a siphon aqueduct, the worst condition of uplift on the floor occurs when ________
View solution
Q. To reduce the cost of the CD works we resort to _____
View solution
Q. The greater is the fluming, the greater is the length of upstream and downstream transition wings.
View solution
Q. Which of the following wings protect the earthen slopes of the canal and also guide the drainage water?
View solution
Q. The head loss through a siphon barrel is usually given by Unwin’s formula by neglecting velocity of approach as HL = [1 + F₁ + F₂. L/R] V²/2g, where F₁ and F₂ respectively represent the coefficient of head losses due to?
View solution
Q. The floor of a siphon aqueduct needs to be designed for conditions when?
i. The canal and drainage are flowing full
ii. The canal is full and there is no drainage discharge
iii. The canal is empty and drainage discharge is full
View solution
Q. A siphon aqueduct is constructed at a canal crossing site where drainage HFL was 212.2 m by allowing an afflux of 0.4 m at high flood discharge. At this site, the water level downstream of the crossing at the same high flood will be _________
View solution
Q. Calculate the depth of cut-off for scour holes for an irrigation channel of F.S.Q equal to 354 cumecs and H.F.Q of natural drainage equal to 600 cumecs. Assume the value of friction factor as 1.
View solution
Q. Calculate the value of hydraulic mean radius for a channel designed by Lacey’s theory which has a mean velocity of 1m/sec. The silt factor can be taken as unity.
View solution
Q. Which of the following is usually adopted for contraction and construction joints?
View solution
Recommended Subjects
Are you eager to expand your knowledge beyond Irrigation Engineering? We've handpicked a range of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!