Industrial Engineering and Production Management MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Industrial Engineering and Production Management, a fundamental topic in the field of Mechanical Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Industrial Engineering and Production Management MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Industrial Engineering and Production Management mcq questions that explore various aspects of Industrial Engineering and Production Management problems. Each MCQ is crafted to challenge your understanding of Industrial Engineering and Production Management principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Mechanical Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Industrial Engineering and Production Management MCQs are your pathway to success in mastering this essential Mechanical Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Industrial Engineering and Production Management. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Industrial Engineering and Production Management knowledge to the test? Let's get started with our carefully curated MCQs!

Industrial Engineering and Production Management MCQs | Page 3 of 17

Discover more Topics under Mechanical Engineering

Q21.
A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the
Discuss
Answer: (b).variable cost line
Discuss
Answer: (d).all of the above
Q23.
Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is __________ the standard time.
Discuss
Answer: (b).one-half
Discuss
Answer: (d).all of the above
Q25.
Generally PERT is preferred over CPM for the purpose of project evaluation.
Discuss
Answer: (a).Yes
Q26.
The bonus increases in proportion to the increase in efficiency. This statement applies to
Discuss
Answer: (c).Emerson's efficiency plan
Discuss
Answer: (d).all of the above
Discuss
Answer: (d).all of these
Discuss
Answer: (d).all of these
Discuss
Answer: (d).none of the above