Surveys and Construction of Railway Lines MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Surveys and Construction of Railway Lines, a fundamental topic in the field of Railway Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Surveys and Construction of Railway Lines MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Surveys and Construction of Railway Lines mcq questions that explore various aspects of Surveys and Construction of Railway Lines problems. Each MCQ is crafted to challenge your understanding of Surveys and Construction of Railway Lines principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Railway Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Surveys and Construction of Railway Lines MCQs are your pathway to success in mastering this essential Railway Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Surveys and Construction of Railway Lines. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Surveys and Construction of Railway Lines knowledge to the test? Let's get started with our carefully curated MCQs!

Surveys and Construction of Railway Lines MCQs | Page 7 of 8

Q61.
In which method of Plate laying a temporary line is laid by side the of the proposed railway track?
Discuss
Answer: (a).Tram line method
Q62.
On what type of Terrain is the Tram line method most useful?
Discuss
Answer: (c).Flat terrain
Discuss
Answer: (a).Trucks travelling on a service road
Q64.
For what type of banks, Borrow pits are provided only on one side of the track?
Discuss
Answer: (b).Low banks
Discuss
Answer: (a).For providing services for running the trains
Q66.
Which is the most widely used method for Track linking and Plate laying?
Discuss
Answer: (c).Telescopic method
Q67.
In telescopic method, the track material is carried to the site through the same track which is to be laid further.
Discuss
Answer: (a).True
Discuss
Answer: (c).Junction of existing line and new line to be constructed
Q69.
Which special type of rail carrier is used for carrying of rails?
Discuss
Answer: (a).Anderson rail carrier
Q70.
For which type of sleepers rail screws are used?
Discuss
Answer: (d).Wooden sleepers