Surveys and Construction of Railway Lines MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Surveys and Construction of Railway Lines, a fundamental topic in the field of Railway Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Surveys and Construction of Railway Lines MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Surveys and Construction of Railway Lines mcq questions that explore various aspects of Surveys and Construction of Railway Lines problems. Each MCQ is crafted to challenge your understanding of Surveys and Construction of Railway Lines principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Railway Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Surveys and Construction of Railway Lines MCQs are your pathway to success in mastering this essential Railway Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Surveys and Construction of Railway Lines. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Surveys and Construction of Railway Lines knowledge to the test? Let's get started with our carefully curated MCQs!

Surveys and Construction of Railway Lines MCQs | Page 4 of 8

Q31.
The survey done on site usually covers a width of 200m on either side of the alignment.
Discuss
Answer: (a).True
Q32.
Which among the following is not a part of the report prepared after Preliminary survey?
Discuss
Answer: (d).Population projection and volume projection of Traffic
Discuss
Answer: (a).After the particular Railway line to be constructed is decided
Discuss
Answer: (d).To prepare working details and make accurate cost estimates
Q35.
In Preliminary survey the total alignment is traversed with a Theodolite, but it is not necessary in Final location survey.
Discuss
Answer: (b).False
Discuss
Answer: (c).At tangent points and along the centre line
Discuss
Answer: (d).Ease and minimum cost of construction, correct obligatory points and potential for high speeds
Q38.
In Characteristics of the Project Areas the geographical features of the country are given. These features do not affect the _______
Discuss
Answer: (d).hauling capacity of the train
Discuss
Answer: (d).Maximum speed potential, axel load and loading standard of the bridges
Q40.
The Permanent way section of the report does not give details about which of the following aspects?
Discuss
Answer: (b).The depth of the Ballast cushion
Page 4 of 8