Tunnelling MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Tunnelling, a fundamental topic in the field of Civil Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Tunnelling MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Tunnelling mcq questions that explore various aspects of Tunnelling problems. Each MCQ is crafted to challenge your understanding of Tunnelling principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Civil Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Tunnelling MCQs are your pathway to success in mastering this essential Civil Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Tunnelling. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Tunnelling knowledge to the test? Let's get started with our carefully curated MCQs!

Tunnelling MCQs | Page 3 of 5

Discover more Topics under Civil Engineering

Q21.
Which one of the following methods is adopted for permanent drainage of tunnels :
Discuss
Answer: (d).All the above.
Discuss
Answer: (d).All of the above.
Q23.
For tunnels exceeding 300 m in length, the grade should be provided below
Discuss
Answer: (c).75% of the ruling gradient
Q24.
The method of draining in the tunnels, is generally known as
Discuss
Answer: (d).All of the above.
Discuss
Answer: (d).All of the above.
Q26.
To attain the required shape of the tunnel section, we use :
Discuss
Answer: (b).trimmers
Discuss
Answer: (d).all the above.
Q28.
Which one of the following methods of tunnelling does not require the use of time bearing :
Discuss
Answer: (d).All the these.
Q29.
For highways, tunnelling is preferred to if the open cut exceeds :
Discuss
Answer: (b).15 metres depth
Q30.
The following operations are required for tunnelling in rocky terrain :

1. Removing the foul gases
2. Marking the tunnel profile
3. Setting up and drilling
4. Checking misfire
5. Mucking

The correct sequence is :
Discuss
Answer: (d).2 3 1 4 5