Construction Management MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Construction Management, a fundamental topic in the field of Civil Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Construction Management MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Construction Management mcq questions that explore various aspects of Construction Management problems. Each MCQ is crafted to challenge your understanding of Construction Management principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Civil Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Construction Management MCQs are your pathway to success in mastering this essential Civil Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Construction Management. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Construction Management knowledge to the test? Let's get started with our carefully curated MCQs!

Construction Management MCQs | Page 1 of 9

Discuss
Answer: (c).activity of excavation which takes 8 units of time
Q2.
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

a.

A

b.

B

c.

C

d.

D

Discuss
Answer: (c).C
Q3.
Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:

a.

A

b.

B

c.

C

d.

D

Discuss
Answer: (b).B
Q4.
For the network shown in the given figure, the expected time for the activity
Discuss
Answer: (d).all the above
Q5.
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the
Discuss
Answer: (a).19
Q6.
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
Discuss
Answer: (d).25
Q7.
The performance of a specific task in CPM, is known
Discuss
Answer: (c).Activity
Discuss
Answer: (d).All the above.
Discuss
Answer: (d).none of these.
Q10.
Completion of an activity on CPM network diagram, is generally known
Discuss
Answer: (d).All the above.
Page 1 of 9