Construction Management MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Construction Management, a fundamental topic in the field of Civil Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Construction Management MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Construction Management mcq questions that explore various aspects of Construction Management problems. Each MCQ is crafted to challenge your understanding of Construction Management principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Civil Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Construction Management MCQs are your pathway to success in mastering this essential Civil Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Construction Management. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Construction Management knowledge to the test? Let's get started with our carefully curated MCQs!

Construction Management MCQs | Page 6 of 9

Discuss
Answer: (d).all the above.
Discuss
Answer: (d).All the above.
Q53.
Which one of the following represents an event ?
Discuss
Answer: (a).concrete cured
Discuss
Answer: (b).Bar chart establishes the interdependency of one event on another
Discuss
Answer: (d).all the above.
Q56.
If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
Discuss
Answer: (a).(t1 - t2) - t
Discuss
Answer: (d).All the above.
Q58.
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

a.

1

b.

2

c.

3

d.

4

Discuss
Answer: (a).1
Q59.
For the execution of a project, a contractor is
Discuss
Answer: (d).all the above.
Discuss
Answer: (b).heavy construction
Page 6 of 9