Construction Management MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Construction Management, a fundamental topic in the field of Civil Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Construction Management MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Construction Management mcq questions that explore various aspects of Construction Management problems. Each MCQ is crafted to challenge your understanding of Construction Management principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Civil Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Construction Management MCQs are your pathway to success in mastering this essential Civil Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Construction Management. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Construction Management knowledge to the test? Let's get started with our carefully curated MCQs!

Construction Management MCQs | Page 4 of 9

Discover more Topics under Civil Engineering

Q31.
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
Discuss
Answer: (c).dummy
Q32.
Henry Gantt developed Bar charts for planning and scheduling of projects in
Discuss
Answer: (b).1900
Q33.
The most popular type of organisation used for Civil Engineering Constructions, is
Discuss
Answer: (a).line organisation
Discuss
Answer: (d).All the above.
Q35.
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
Discuss
Answer: (d).all the above.
Q36.
Final technical authority of a project lies with
Discuss
Answer: (d).Chief Engineer.
Q37.
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
Discuss
Answer: (d).all the above.
Q38.
Works costing less than Rs. 20,000 are treated as
Discuss
Answer: (c).minor projects
Discuss
Answer: (d).none of these.
Q40.
Bar charts are suitable for
Discuss
Answer: (a).minor works
Page 4 of 9