Question
a.
The mean depth is the average of depths of two consecutive sections
b.
The area of mid-sections is calculated by using mean depth
c.
The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two sections
d.
(a), (b) and (c) of the above.
Posted under Civil Engineering
Interact with the Community - Share Your Thoughts
Uncertain About the Answer? Seek Clarification Here.
Understand the Explanation? Include it Here.
Q. In the mid-section formula
Similar Questions
Explore Relevant Multiple Choice Questions (MCQs)
Q. The item of steel work which is measured in sq.m, is
View solution
Q. If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by
View solution
Q. The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is
View solution
Q. While estimating a reinforced cement structure, the omitted cover of concrete is assumed
View solution
Q. The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as
View solution
Q. Pick up the incorrect statement from the following:
View solution
Q. If tensile stress of a steel rod of diameter D is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is
View solution
Q. Pick up the correct statement in case of water supply.
View solution
Q. In case of laying gullies, siphons, intercepting traps, the cost includes
View solution
Q. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and
View solution
Q. The height of the sink of wash basin above floor level is kept
View solution
Q. While preparing a detailed estimate
View solution
Q. The plinth area of a building not includes
View solution
Q. For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is
View solution
Q. The minimum width of a septic tank is taken
View solution
Q. The item of the brick structure measured in sq.m, is
View solution
Q. The inspection pit or chamber is a manhole provided in a base drainage system
View solution
Q. Pick up the excavation where measurements are made in square metres for payment.
View solution
Q. The expected out turn of 2.5 cm cement concrete floor per manson per day
View solution
Q. A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.
View solution
Recommended Subjects
Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!