Estimating and Costing MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Estimating and Costing, a fundamental topic in the field of Civil Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Estimating and Costing MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Estimating and Costing mcq questions that explore various aspects of Estimating and Costing problems. Each MCQ is crafted to challenge your understanding of Estimating and Costing principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Civil Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Estimating and Costing MCQs are your pathway to success in mastering this essential Civil Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Estimating and Costing. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Estimating and Costing knowledge to the test? Let's get started with our carefully curated MCQs!

Estimating and Costing MCQs | Page 6 of 10

Discover more Topics under Civil Engineering

Q51.
The area is measured correct to the nearest
Discuss
Answer: (a).0.01 sqm
Q52.
Cost of fittings and their fixing is specified for the following sanitary fittings
Discuss
Answer: (d).All the above.
Q53.
The volume is measured correct to the nearest
Discuss
Answer: (a).0.01 cum
Discuss
Answer: (d).All the above.
Q55.
Pick up the item whose weight is added to the weight of respective item, is
Discuss
Answer: (d).All the above.
Q56.
Size, capacity and materials need be specified for
Discuss
Answer: (d).All the above.
Q57.
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
Discuss
Answer: (c).1500 m³
Q58.
The expected out turn for earth work in excavation in ordinary soil per mazdoor per day is
Discuss
Answer: (c).3.00 cum
Discuss
Answer: (c).Top of P trap W.C.
Q60.
According to Indian Standards Institute, the actual size of modular bricks is
Discuss
Answer: (c).19 cm x 9 cm x 9 cm