Estimating and Costing MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Estimating and Costing, a fundamental topic in the field of Civil Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Estimating and Costing MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Estimating and Costing mcq questions that explore various aspects of Estimating and Costing problems. Each MCQ is crafted to challenge your understanding of Estimating and Costing principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Civil Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Estimating and Costing MCQs are your pathway to success in mastering this essential Civil Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Estimating and Costing. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Estimating and Costing knowledge to the test? Let's get started with our carefully curated MCQs!

Estimating and Costing MCQs | Page 2 of 10

Discuss
Answer: (d).(a), (b) and (c) of the above.
Q12.
The item of steel work which is measured in sq.m, is
Discuss
Answer: (d).All the above.
Q13.
If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by
Discuss
Answer: (d).All the above.
Q14.
The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is
Discuss
Answer: (b).L + 2 x 0.42 d
Discuss
Answer: (d).All the above.
Q16.
The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as
Discuss
Answer: (d).Surface excavation.
Discuss
Answer: (c).Cubic contents are measured to the nearest 0.1 cm m
Q18.
If tensile stress of a steel rod of diameter D is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is
Discuss
Answer: (d).59 D
Discuss
Answer: (d).All the above.
Q20.
In case of laying gullies, siphons, intercepting traps, the cost includes
Discuss
Answer: (d).All of these.
Page 2 of 10