Estimating and Costing MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Estimating and Costing, a fundamental topic in the field of Civil Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Estimating and Costing MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Estimating and Costing mcq questions that explore various aspects of Estimating and Costing problems. Each MCQ is crafted to challenge your understanding of Estimating and Costing principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Civil Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Estimating and Costing MCQs are your pathway to success in mastering this essential Civil Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Estimating and Costing. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Estimating and Costing knowledge to the test? Let's get started with our carefully curated MCQs!

Estimating and Costing MCQs | Page 7 of 10

Q61.
While estimating the qualities for the construction of a building, the correct metric unit is
Discuss
Answer: (d).Litre for capacity
Q62.
The slope of the oultet of 'P trap' below the horizontal is kept
Discuss
Answer: (d).14°
Discuss
Answer: (b).The gully trap collects waste water from the kitchen, sink, wash basins, etc.
Discuss
Answer: (d).M.S. reinforcement of R.C.C. works.
Discuss
Answer: (d).All the above.
Q66.
The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by prismoidal formula, is
Discuss
Answer: (b).3225 m³
Q67.
The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended
Discuss
Answer: (b).150 mm
Discuss
Answer: (d).All the above.
Q69.
The weight of an item is measured correct to nearest
Discuss
Answer: (d).1.00 kg
Q70.
Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds
Discuss
Answer: (d).5.0%
Page 7 of 10